Thursday

A High Time on the 4th!

A million details high up on the roof before the roofing can actually be installed. Blocks and tie downs and brackets and a million more nails.

Brad working on the ridge beam















Erin's first trip to the top















The rafters and purlins make some beautiful shadows

Happy 4th of July!



We celebrate the 4th with new roofing!












Tuesday

Working Late

Well, Ed installed this way cool 5" half round galvanized gutter, but all the pictures show Brad putting the finishing touches on it, by attaching the downspout. This gutter detail with downspout is Brad's innovative creation. The roof will join the gutter on July 4 -- an all day family roofing party.



















Late night work sessions are eased by a campfire at the site with dinner on the grill. Ed, Brad and Erin enjoying the fire.


Brad and Dianne

A little philosophy over the wood pile...

Supporting the Porch


These sono tubes will hold the concrete to support the steel posts that will support the main house porch roof. Austin and Brad work to get every direction straight and level before securing the tubes, and then the posts, with hand mixed concrete. The cement truck will top them off on Thursday during the retaining wall pour. Then, at a future time, the slab will be poured around them hiding the footings entirely.


The Barn is Attracting Attention!

Talia was walking by and stopped
to see what we are doing




















John, Kay and Ed. John comes by often as he's
a recycling buff and loves to see what we're doing















Brad and Tim of Heavy Metal Works check out a
prototype leg for our dining room tables.

Preparing for Another Pour

The pour date has slipped a little, but now it's locked in -- we're pouring on Thursday. The complexity of the forms, rebar and steel is another eye opener, especially as they all come together at the same level with the angles lining up.